Pressure Testing of Chilled Water Piping System
Pressure Testing of Chilled Water Piping System:
- The Chilled water piping shall be tested according to the system working pressure i.e. 1.5 times the working pressure. and/ or PN ratings of the pipes, pipe fittings and valves used in the piping.
- The piping may be tested in sections or total, depending on site requirements and as per consultant advice.
- Estimate the piping volume and make arrangement for required quality of clean water.
- Arrange for temporary piping/ hose pipe connections for filling and draining water.
- Fix the temporary valves at air vent/ drain points and pressure gauges.
- Fill the piping system with clean water through a temporary pump and obtain the test pressure if no leakage is observed.
- If leakages are observed, arrange the leakage immediately. If leakages are major, isolate the leaking portion with nearest isolating valve and/ or stop the water filling.
- Rectify the leakages and again fill with water until no leakages throughout the entire piping system is observed.
- After no leakage is observed pressurize the system using hydraulic test pump up to full pressure.
- During pressurization observe the joints and entire piping system for leakages.
- Observe the pressure gauges readings for 4 hours and sure that there is no drop in gauge pressure. System pressure to be 1.5 times than the actual working pressure.
4 comments:
It is very useful information. Thank you.
Chilled Water Distribution
Pipeline Cathodic Protection
160psi after 24hrs, 150psi how percentage drop is that?
Can you show me a computation
How many percentage drop is that? Can you show me a computaion? Tahnk you